You estimated 6 weeks. The last three of these took 12. What now?
Your team estimates a comparable workstream at 6 weeks, but the last three similar projects all took ~12 weeks. How do you reconcile?
Multiple choice · Answer in the app
Want the answer graded?
Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.
principle
Anchor on history, not optimism; analogous estimates beat fresh guesses when data exists.