Issue №1026 · wbs · foundational

Your WBS adds up to 110% of the project. What went wrong?

Auditing the WBS, you find work duplicated across two work packages. What's the structural fix?

Multiple choice · Answer in the app


Want the answer graded?

Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.

principle

100% rule: the WBS must capture all work, no more, no less.