Reserves are gone in week 6. The date is still green. Concerned?
Your management reserve is fully consumed but the project is on schedule. How do you read this?
Multiple choice · Answer in the app
Want the answer graded?
Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.
principle
When contingency reserves are spent, the project is in trouble even if the date hasn't slipped.