Issue №1048 · schedule · foundational

An activity has 5 days float. The owner takes them all. Right call?

An activity manager uses all 5 days of float on their task because their team is busy. Critical path becomes vulnerable. What's the structural fix?

Multiple choice · Answer in the app


Want the answer graded?

Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.

principle

Float belongs to the project, not to the activity owner.