Two weeks late. Crash or fast-track?
Behind schedule. Crashing (adding resources) is expensive; fast-tracking (parallelising) increases rework risk. Which to choose?
Multiple choice · Answer in the app
Want the answer graded?
Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.
principle
Fast-tracking trades risk for time; crashing trades cost for time. Same problem, different lever.