Issue №1062 · resource · intermediate

Your plan has a 60-hour week. Level or smooth?

The schedule shows a 60-hour week for a key engineer. Project date is firm. Which method fits?

Multiple choice · Answer in the app


Want the answer graded?

Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.

principle

Resource leveling protects people; resource smoothing protects the date. Different goals, different methods.