Issue №1184 · budget · foundational

On schedule, over budget. What's the trade?

Project shows SPI 1.05 (ahead of schedule) and CPI 0.85 (over budget). What's likely happening?

Multiple choice · Answer in the app


Want the answer graded?

Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.

principle

SPI > 1 with CPI < 1 means you're spending money to maintain schedule; make that explicit, not implicit.