On schedule, over budget. What's the trade?
Project shows SPI 1.05 (ahead of schedule) and CPI 0.85 (over budget). What's likely happening?
Multiple choice · Answer in the app
Want the answer graded?
Daily PM gives you one prompt every weekday. Ten focused minutes. A graded answer back. The first three are free.
principle
SPI > 1 with CPI < 1 means you're spending money to maintain schedule; make that explicit, not implicit.